Main parameters ;

  • Mill throughput
  • Operation hour
  • Estimate effluent production - 0.8 to 1.0 t/t FFB
  • Daily effluent production
  • HRT = Liquor volume / Daily effluent production

Legend ;

  1. d - Working depth of liquor
  2. L1 - Length of pond at top water level
  3. L2 - Length of pond at bottom water level
  4. W1 - Width of pond at top water level
  5. W2 - Width of pond at bottom water level
  6. Tph - Tonne per hour of FFB process
  7. t/t - Tonne per tonne

Formula used for calculating pond/liquor volume ;

V = Depth [ A + a + /A.a ] x 1/3

Where,

  • V - Volume
  • A - Area of pond at top water level or L1 x W1
  • a - Area of pond at bottom water level or L2 x W2
  • d - Working depth of water or liquor

# /A - square root of A

3 comments:

Jagan Jai said...

In that industries when we get the project or tender For Maintenance purpose. First the safety dept analysis the value of the work. If incase the maintenance for mep. They hired the product in some contractor for example Scissor lift, Boom Lift, Movable Aluminium Scaffolding

Pradeep Singh said...

All MNC company need interior designs for new look. Its help look and feel gud.

Pradeep Singh said...

U look sathiyam cinemas Pantry the Modular Kitchen In Chennai is more preferred for looking and sound effects